The following schedule lists the sequence of events for a typical system installation:

  • 60 days before installation

    • Floor plan design completed and mailed to Hewlett-Packard (if required to be an HP task)

  • 30 days before installation

    • Primary power and air conditioning installation completed

    • Telephone and data cables installed

    • Fire protection equipment installed

    • Major facility changes completed

    • Special delivery requirements defined

    • Site inspection survey completed

    • Delivery survey completed

    • A signed copy of the site inspection and delivery survey mailed to Hewlett-Packard

    • Site inspection and predelivery coordination meeting arranged with a Hewlett-Packard representative to review the inspection checklist and arrange an installation schedule.

  • 7 days before installation

    • Final check made with an Hewlett-Packard site preparation specialist to resolve any last minute problems

NOTE: Not all installations follow a schedule like the one noted above. Sometimes, an hp server is purchased through another vendor which can preclude a rigid schedule. Other conditions could also prevent following this schedule. For those situations, consider a milestone schedule.
  • Site Preparation - schedule with the customer as soon as possible after the order is placed.

  • Site Verification - schedule with the customer a minimum of one to two days before the hp server is scheduled to be installed.